Using the ESMS
120
Scheduling Power State Changes
To schedule individual or multiple server power state changes, perform the following steps:
1. Select Scheduled and enter the date and time for the power state change to occur.
2. Select the desired power status from the drop down menu.
3. Select the servers to receive the state change signal in the Power Status panel.
Figure 108 Scheduling Power State Changes
4. Click Submit. The requested power state changes are added to the Power Control Schedule Status panel.
Figure 109 Submitting Power State Changes
When the date and time specified arrives, the requested power state change is sent to the selected remote serv-
er(s).
Note:
Scheduled changes that have expired are retained by the schedule status panel
until the administrator clicks Clear.